Two road projects are underway on the west side of Northwest Hills right now, and they won't finish anywhere near the same time. The City of Austin's rebuild of Spicewood Springs Road, between Mesa Drive and Loop 360, is now set for summer 2027. TxDOT's work at RM 2222 and Loop 360 started in April 2026 and is expected to run until late 2029. If the targets hold, the neighborhood's own street finishes about two years before its main highway interchange. So for most of the next three years, the two exits are at different stages, and the order they finish in matters more than either one alone.
These are the dates the city and TxDOT have published as of mid-October 2026, sorted by when each project ends.
When Westlake Drive wraps up, Courtyard and RM 2222 becomes the only active construction zone on the whole 14-mile Loop 360 program, and it's the one closest to Northwest Hills.
The city project carries $31 million in funding from the 2016 Mobility Bond's Regional Mobility Program, and construction started in December 2023. The finished road will have two lanes in each direction, a raised median with left-turn bays, a shared-use path on both sides, and new stormwater facilities.
Community Impact reported that the city's Aug. 11 update moved substantial completion from late 2026 to summer 2027 after weather delays in the spring and summer. That city update also laid out the fall work. Shared-use paths on both sides of the road started in September, and crews are continuing with rain gardens and paving of the travel lanes through fall 2026. In other words, the work along Spicewood Springs this season is the paths, the rain gardens and the new pavement, all of which come near the end of a road project.
The posted work hours matter for daily trips. The city lists roadwork on weekdays from 9 a.m. to 4 p.m. and on weekends from 7 a.m. to 7 p.m. On weekdays, that window starts after the morning school and office rush and ends before the evening one. On weekends it covers most of the day, so a Saturday errand down Spicewood Springs is more likely to pass active crews than a 7:45 a.m. weekday drive.
TxDOT describes the Courtyard Drive and RM 2222 project in two parts. It will remove the traffic signal on the Loop 360 mainlanes at Courtyard Drive and build an underpass there. It will also turn RM 2222 at Loop 360 into a diverging diamond interchange and add shared-use paths and sidewalks. Webber is the contractor.
The TxDOT project page splits the work into four phases:
The interchange itself is phase 3 of 4. The heavy RM 2222 rebuild comes after the connector roads, ramps and the Courtyard bridge. By the time crews reach it, Spicewood Springs should be long finished, if the city's summer 2027 target holds.
Some changes have already reached the RM 2222 ramps. Under TxDOT's new traffic pattern, the entrance ramp from eastbound RM 2222 to southbound Loop 360 closes. To head south on 360, drivers now turn right at the RM 2222 signal. The northbound Loop 360 exit ramp to RM 2222 has new lane assignments too: left turn only, left turn or straight, and right turn only. If you take 360 north and exit at 2222, pick your lane before the ramp splits, not at the signal.
The overnight closures TxDOT posted for mid-October show what the bigger disruptions look like on this project. Westbound RM 2222 had rolling closures between Loop 360 and City Park Road on Wednesday, Oct. 14, from 8 p.m. to 5 a.m. The next night, Thursday, Oct. 15, eastbound RM 2222 was cut to one lane between Lakewood Drive and Loop 360, and the westbound RM 2222 entrance ramp to northbound Loop 360 was closed over the same hours. Those dates have passed. TxDOT posts new closures on the same project page, so check it before a late-night airport run or the drive home from a dinner out west on 2222.
Regular construction runs weekdays from 7 a.m. to 7 p.m., plus Saturdays from 7 a.m. to 3 p.m. when needed. TxDOT warns that neighbors may notice more noise, vibration and dust during excavation and night work.
This is where the two schedules meet. TxDOT's Lakewood Drive and Spicewood Springs Road project would remove the mainlane signals at Lakewood Drive and at Spicewood Springs Road (E)/Bluffstone Drive and build overpasses there. It would also remove the mainlane signal at Spicewood Springs Road (W). It was environmentally cleared in summer 2023. But construction depends on funding and isn't expected to start before 2029.
So the rebuilt Spicewood Springs Road, with its median, turn bays and paths, will still end at the same signal-controlled Loop 360 intersections drivers use today. That's likely to last at least through the rest of the decade. TxDOT notes that utility relocation comes before construction and that it may require occasional lane closures. Meanwhile, the city side of the road finishes first.
Spicewood Springs settles into its finished layout around mid-2027, while RM 2222 at Loop 360 is still in the middle of its phases. After that, Spicewood Springs Road is the western route with a finished surface and fixed lanes, and the 2222 interchange keeps changing until late 2029.
| Route | Posted work hours | Current finish target |
|---|---|---|
| Spicewood Springs Road, Loop 360 to Mesa Drive | Weekdays 9 a.m. to 4 p.m.; weekends 7 a.m. to 7 p.m. | Summer 2027 |
| Loop 360 at Courtyard Drive and RM 2222 | Weekdays 7 a.m. to 7 p.m.; Saturdays 7 a.m. to 3 p.m. as needed; posted overnight closures | Late 2029 |
| Loop 360 at Lakewood Drive and Spicewood Springs Road | No construction scheduled; depends on funding | Start as early as 2029 |
Sunday is the only day not on the RM 2222 project's regular schedule. Spicewood Springs does list weekend hours, and those include Sundays.
Two November dates will put more cars on these routes. Community Impact reported that Tumble 22 is scheduled to open Nov. 7 at the Arboretum, 9761 Great Hills Trail, Ste. B. Later in the month, Mozart's Coffee Roasters starts its Festival of Lights, which Visit Austin lists from Nov. 21, 2026, through Jan. 3, 2027. If you're heading out for an evening at either one, check the TxDOT closure list the same afternoon. Overnight closures on this project have started at 8 p.m.
The City of Austin's Spicewood Springs Road project page and the TxDOT Courtyard Drive and RM 2222 page are where new dates show up first. The city posts schedule changes as dated updates, and TxDOT lists upcoming lane closures night by night.
These road schedules overlap with how buyers will see the west side of Northwest Hills in 2027 and beyond. If you're thinking about listing before or after Spicewood Springs Road finishes, Merissa Anderson Group can talk through the timing with you. Let's write your story of home. Schedule a free consultation.